Hayward demolition permit checklist
The City of Hayward's Development Services handout, revised in 2019, lists the items that go with a demolition permit: a job number from the Bay Area district, a PCB screening assessment form, a construction and demolition debris recycling statement, and a PG&E disconnection letter where utilities are removed. It also gives demolition hours as Monday to Saturday 7 a.m. to 7 p.m. and Sunday and holidays 10 a.m. to 6 p.m. The handout is several years old, so confirm the current list at the Permit Center, 777 B Street.
The J# is issued through the district's online notification system, and its start and end dates are firm, so revise them if the schedule moves. The City's remodel permit pages do not list an asbestos step. The air district rule sets when a remodel needs a J#: when removal reaches the notification quantities, or when it is done dry. PCB screening is a separate hazardous-material topic on the same paperwork. Cost follows the number of positive materials, their quantities and whether demolition follows.